COCOMO II Construction Phase Estimates;
CS577b Rough Team Size
COCOMO II PM
577b
Team Size =
1.67
577b Team Member = (10 Weeks) (12 * Project-hr / Week) = 120 Project-Hr
1.67 COCOMO II PM = 1.67 (152 PM) ( .66 * Project-Hr /Total Hr) * (.72) ** = 120 project-Hr
*: .66 of day doing project work
**: .72% of estimation effort in Construction Phase
8.34 COCOMO PM = 5 Team Members