CS510 Homework #5
30 Points, Due Friday, Sep. 28, 2007
Business Case Analysis Using COCOMO II.2000 Post Architecture Formulas
Precision Products, Inc.(PPI) has a software staff of 200 people supporting its product line of industrial electronic devices. It has been exploring the use of the software Capability Maturity Model to improve its software performance. An initial assessment has indicated that the company has just reached a Low level (Upper level 1) on the COCOMO II rating scale for Process Maturity(PMAT). Some other characteristics of its average project are:
PPI is considering a process maturity investment effort to bring its CMM Level up to 2 and benefit from the project effort reduction estimation by COCOMO II via the reduction in the scale exponent E for its projects. The process maturity investment will require two years at an annual expenditure of :
Assuming that all PPI software projects and people have the average characteristics above, perform a simple business case analysis (exculding present value efforts) for the process maturity investment, including:
If future costs and savings were discounted at a rate of D=0.95 per year, would the following increase or decrease: