| Activity No. | Duration (weeks) | Predecessor Activities | Activity |
| A1 | 2 |   | Indentify, prioritize needed capabilities |
| A2 | 1 |   | Identify, prioritize cost, schedule, and quality constraints |
| A3 | 3 | A1, A2 | Evaluate COTS alternatives |
| A4 | 2 | A1, A2 | Evaluate custom alternatives |
| A5 | 3 | A3, A4 | Evaluate mixed COTS/custom alternatives |
| A6 | 3 | A5 | Identify, resolve technical risks |
| A7 | 4 | A5 | Identify, resolve management risks |
| A8 | 2 | A6, A7 | Decide whether to proceed, which alternatives to elaborate |
| A9 | 1 | A6, A7 | Document results |
|   |   | A8, A9 | Finish |